How long does a bathroom remodel take?expand_more
Three to five weeks of active work for a standard full remodel, assuming materials are on site before demo. Waiting on custom glass or a backordered vanity is what stretches projects, so order everything early.
Can I keep using the bathroom during the work?expand_more
Not this one. If it is your only full bathroom, talk with the contractor about sequencing so the toilet goes back into service as early as possible, and plan for a few days without a shower at home.
Is a tiled shower better than an acrylic surround?expand_more
Tile looks better and lets you size the shower however you like, but it depends entirely on the waterproofing behind it. A quality acrylic or solid-surface unit is genuinely a fine choice for a rental or a secondary bath, and it installs in a fraction of the time.
Do I need to move the plumbing to get a better layout?expand_more
Usually less than you would think. Swapping a vanity for a wider one or changing a shower's door swing rarely requires moving drains. Relocating the toilet is the expensive move because the waste line has to be rerouted through the floor framing.
What should be in a written bid?expand_more
Named allowances for tile, vanity, fixtures, and glass; the waterproofing system by name; who supplies what; the permit; a payment schedule tied to milestones; and a contingency for rot. If a bid is one line and one number, ask for it broken out before you sign anything.
How do I verify a Hillsboro bathroom contractor?expand_more
Use Oregon CCB consumer tools, match the exact legal name and license number, confirm active status and review the available history. Also identify the licensed businesses performing regulated specialty work.
What should happen before walls are closed?expand_more
Complete required rough inspections, document waterproofing and concealed work, test plumbing, confirm ventilation ducting and photograph blocking or utilities that may matter later.
When should final payment be due?expand_more
After the agreed scope and punch list are complete, required final inspections are documented, fixtures and ventilation operate correctly, warranties are delivered and the room and access path are clean.